Wheel change
Home Up Outdoors Work area Inside an ICE Under an ICE Wheel change

 

Nederlandse Site

NY Signal drawn by 3rd PlanIt

TrackPlanning.com

NY Signal drawn 
with
3rd PlanIt by Walter Griffin

Click to subscribe to 3rd PlanIt


This remarkable sequence shows the efficiency of the Hamburg ICE Works. These photos were taken with a digital camera that captures the time each photo was taken. Here, a new wheelset arrives at 13:57:50. The old wheelset had been removed in the same manner the new one will be installed.

In the background, a machine has been positioned for the operation. This machine both lifts wheelsets and separates segments of special repair track above it.

The machine starts to move the segment of repair rail away from its normal position, to the outside. The same operation is happening to the track segment on the other side.

The new wheelset is being bolted into place as the repair machine replaces the repair rails. The time on the photograph shows 14:06:14. The total time to position the new wheelset is about 10 minutes!

This model of the wheelset change machine is on display for visitors.